Skip to content

Sugar refinery is sweet on our steam turbine services

Rapid response on a steam turbine forced outage saves months on repair lead time for a major sugar refiner

Goals
  • Reduce Forced Outage Rate
  • Increase reliability
  • Reduce Downtime
Sectors
  • Power generation
Asset
  • Steam Turbines
  • Generators
  • Field Services
Location
Northern California, US
Sugar refinery is sweet on our steam turbine services

Fast response to a forced outage

One of the world’s largest refiners and marketers of cane sugar, producing around 6 million metric tons of sugar each year, owns and operates numerous sugar refineries across North America and also in Europe.

One of these refineries, based in Northern California, processes over 700,000 tons of cane sugar each year – that’s enough sugar to go in more than 35 billion cans of soda or 152 billion donuts. To do so, the sugar refinery relies on two 5 MW steam turbines to power their operation. These are mature Westinghouse units, commissioned around 1957. 

Before 2023, while we had worked at other facilities in the parent company’s portfolio, we hadn’t undertaken any work at this particular site. But we had partnered with a nearby power generation facility. In early 2023, the power plant gave the sugar refinery a reference for us.

Within two weeks, we received an enquiry. One of the sugar refinery’s two steam turbines had gone into a forced outage. Every day it was down, the sugar refinery was losing money and losing the capacity to produce sugar. Could we help?

A candy-do attitude keeps repairs short and sweet

Our project manager received a call on a Friday afternoon briefing him on the situation. By the Monday morning, we had a contract in place for a forced outage and had arrived on site ready to start diagnosing.

The client suspected a grounded generator stator had caused the failure. On inspection, we discovered it was in fact the rotor that was grounded, although the stator was in poor shape. One of the windings had lost its insulation and shorted to the body component.

From the outset, we knew we would have to manufacture two rows of steam turbine blades. But since refurbishing the generator and getting it back online necessitated a longer lead time, our scope of work evolved to include a steam turbine major and stator rewind. It also included work on numerous ancillary items such as the oil pumps, pressure relief valves, and the control valve actuators.

As is the case with many forced outages, we discovered additional issues that had to be addressed. Our client also requested an operating speed balance. When we did that, we found the journal bearings had been plated incorrectly during someone else’s previous repair.

One of the benefits for the client in partnering with us, however, was that – unlike other providers – we didn’t have to farm out work to third parties. We were able to do everything in-house.

Many different EthosEnergy facilities and teams were involved in getting the unit back up and running:

On-site, in-house, and back online

The OEM had proposed removing the whole generator to repair it off site. That would have been a monumental task, costing in the region of millions of dollars. But we were able to repair the stator in situ at a fraction of the cost.

Also, because of our in-house capabilities, we helped shorten lead times by a considerable margin. While the steam turbine was out of service, the client was paying a sweet $35,000 a day in rental and fuel costs for the auxiliary equipment it needed to run the facility. So being able to cut lead times by a few months made an enormous difference.

Just as we were commissioning the first unit, the second unit went into a forced outage. But because of budgeting constraints, the client didn’t want us, at this stage, to repeat everything we had done on the first unit. So we focused on getting the turbine back online. We inspected and tested the generator, rewound the field, and reassembled the unit.

Off the back of this successful project execution, EthosEnergy was chosen to carry out the full scope of work on unit two in the future - both the steam turbine and generator stator.

Contact us

Whether you have a question about our services or capabilities, or how we can help you solve a challenge, we’d love to hear from you.

What can we help you with today?

QA - EDIT