Gas turbine rotor overhaul
EthosEnergy was contracted to provide gas turbine rotor overhaul for a European refinery
- Goals
-
- Life Extension
- Sectors
-
- Power generation
- Asset
-
- Heavy Gas Turbines
- Location
- Europe
Project Overview
EthosEnergy was contracted to provide gas turbine rotor overhaul for a European refinery. This included two off Frame 6B gas turbine rotor assemblies.
Key Challenges
- Supply of competitively priced APM® parts matching or exceeding OEM quality
- Expedited qualification and approval of EthosEnergy workshop facility in Turin, Italy
- Residual Life Assessments and Life Time Extension of rotors in line with 130,000 Factored Fired Hour target set by customer
The EthosEnergy Solution
- Supply of Stage 1 and 3 blades
- Supply Stage 2 and 3 vanes and shroud block
- Rigorous and comprehensive inspection program in accordance with TIL1576 and EthosEnergy experience as OEM on Westinghouse technology
Project Highlights
- Advanced procurement of complete sets of forgings for critical parts prior to arrival
- Inspection of rotors to ensure expedited project completion
Key Results
- Repeat transactional parts supply since 2010
- Successful approval of EthosEnergy workshop facility in Turin
- EthosEnergy advanced procurement of complete sets of forgings for critical parts prior to arrival and inspection of rotors to ensure expedited project completion
Find out more
-
Rotor Life Extension
Proven and reliable gas turbine rotor end of life solutions for aging fleets, including heavy duty gas turbine GE frame B, E, and F class as well as mature Westinghouse units. EthosEnergy’s solutions have been engineered to meet or exceed the original equipment manufacturer and the recommended end of life.
-
Heavy Gas Turbines
The largest independent service provider of heavy gas turbine services across a wide range of frame types. We are the OEM for Fiat Avio and Mature Westinghouse fleet.